The existing Wastewater Treatment Plant in Devon required an upgrade due to the aging nature of their existing facility and technology. The upgrade project included a sequenced build including the construction and commissioning of the new headworks, followed by the demolition of the old headworks structure. The new secondary treatment was constructed and commissioned prior to demolishing the old secondary treatment process and remaining infrastructure.
The new headworks included fine screens for influent filtration followed by primary filtration/separation through Salsnes Filters. The secondary treatment process included bioreactors/aeration tanks, Membrane Bioreactors as well as Rotary Drum Thickeners and Centrifuges for Solids Handling. UV Filtration closes out the secondary process.
The new facility encompassed provisions for adding primary and secondary filtration equipment as the Town of Devon’s population grows.
Maple Reinders’ work included building new and/or upgrading a total of 5 pump stations and reservoirs for the City of Kelowna
Oxford Riverbend Building 6 is a 79,000 sf warehouse, manufacturing and office facility in Burnaby, BC.
View All
Water/Wastewater Treatment
Maple Reinders designed, constructed and commissioned a new wastewater treatment plant for McCain Foods in Coaldale, Alberta, integrating advanced wastewater treatment, biogas recovery and water recycling systems to improve water and resource efficiency.
Design-Bid-Build contract by Glenmore Ellison Improvement District to construct a pump station and reservoir as part of the Ellison Separation upgrade works
Get Us Working for You
If you have a project youd like to speak to us about, or would like to learn more about our service capabilities, click the link below.
Speak to the Right Team