Metro Vancouver
2016
Richmond, BC
Design/Bid/Build
Process Mechanical
Work on this project involved the supply and installation of new channel bulkhead gates in the live primary effluent channel supply, which required the supply and installation of temporary bulkheads for channel isolation during construction. Work also involved the cutting and removal of a portion of the channel concrete roof deck for gate and frame installation, replacement of the removed platform concrete supports with a new structural aluminum frame, and the supply and installation of a new ladder to access existing aluminum platform and relocate electrical cables and level transmitter to accommodate the new layout of the platform area.